Investment Plan
The total investment of the project is RMB 8.6 billion, with 1,800 mu of planned land use and a planned polylactic acid (PLA) production capacity of 350,000 tons.
The first phase of a 75,000 tons/year lactic acid and 50,000 tons/year PLA smart factory project has officially started construction and is currently undergoing on-load testing and commissioning.
Project Phase One | Project Phase II | |
Investment amount | 2 billion | 6 billion 600 million |
Land area | 300 acres | 1500 acres |
Annual production at full capacity | 50000 tons | 300000 tons |
The pilot production line for producing 300 tons of polylactic acid annually has been put into operation.
Plan for the annual production of 50000 tons of polylactic acid smart factory by PLIITH